2017-2019

PWA

Mahasarakham Project

Water supply expansion, PWA Mahasarakham–(Kantharawichai)–(Borabue) branches, Mueang–Kantharawichai–Borabue, Mahasarakham

฿995M

Project value

48,000 m³/day

Treatment capacity

100 km

Pipe transmission

900 mm

Largest pipe

the challenge

As an education and growth hub, Mahasarakham’s population and water demand rose yearly. Existing production could not keep up, so capacity had to expand in time.

what we delivered

Raw-water station at 186,400 m³/day, new 48,000 m³/day plant, Borabue, Nong Jik and Kantharawichai distribution stations, 500 m³ tower, existing-plant upgrade, plus mechanical, electrical and automation works.

how it was built

Chi River intake with sheet-pile excavation, new 48,000 m³/day plant, three distribution stations, slip-form elevated tower, and mains by open-cut, HDD and pipe jacking.

Impact

Enough added capacity to meet demand, with higher quality from the upgraded existing plant.

©2026 Dynamic Group Products

02-521-5611

info@dynamicgroup.co.th

©2026 Dynamic Group Products

02-521-5611

info@dynamicgroup.co.th

©2026 Dynamic Group Products

02-521-5611

info@dynamicgroup.co.th