2024-2025
MWA
Highway 345 Project
Water main installation and associated works, contract RTP.187(S), Highway 345 from Kanchanaphisek Road junction to Klong Lak Khon
฿83.7M
Project value
—
Treatment capacity
3,573 m
Pipe transmission
1,200 mm
Largest pipe
the challenge
Open-cut and jacked pipe beneath a highway with round-the-clock traffic. Tight traffic control with alternating day and night shifts was required. Long drives under major junctions demanded precise jacking alignment, and temporary mains kept existing customers supplied.
what we delivered
Transmission main 1,200 mm (~363 m by open-cut, shaft laying and jacking), transmission main 1,000 mm (~1,544 m), and distribution main 300 mm (~1,366 m open-cut).
how it was built
Launch and reception shafts of 3.50 × 7.00 m (about 5 m deep) supported jacking drives with pipe segments no longer than 6 m. Each drive ran roughly 150–200 m, followed by tie-ins at connection points.
Impact
Higher distribution capacity for existing customers and an expanded service area.

Pipe jacking — 1,000 mm pipe

Pipe jacking — 1,000 mm pipe

Pipe fittings installation