2024-2027
PWA
Klong 4 Project
Reinforced pressure main along Khlong Luang Road (Pat. 3214) from Thammasat University to Khlong Si distribution station, Kanchanaphisek Road (Highway 9), PWA Khlong Luang branch
฿363M
Project value
—
Treatment capacity
9,723 m
Pipe transmission
1,200 mm
Largest pipe
the challenge
Works ran through dense communities and a busy highway, requiring constant traffic-plan adjustments. DI pipe — new to the company — was used for jacking, so methods had to be studied carefully before each drive.
what we delivered
A transmission main from Thammasat Rangsit to Khlong Si distribution station, boosting supply capacity and pressure in low-flow areas.
how it was built
HDD HDPE 1,000 mm (7,241 m), microtunneled DI 1,000 mm (1,822 m), jacked steel casing 1,200 mm (74 m), and open-cut HDPE 1,000 mm (412 m), plus tie-ins and fittings at Khlong Si station.
Impact
Increased transmission capacity to low-pressure areas in the Khlong Luang–Khlong Si corridor.

HDD — HDPE pipe

HDD — HDPE pipe

Microtunneling

Pipe laying